Power company to build nuclear units

(China Daily HK Edition)
Updated: 2007-01-26 09:37

SHENZHEN: China Guangdong Nuclear Power Group (CGNPG), one of the two major nuclear power station developers of the country, will pump in more funds in the sector while ensuring the safety of each project.

With a home base in this southern China's booming city, the company plans to build two nuclear power generating units each year during 2006-2010 and three units each year during 2011-2015 , company spokesman Zhang Weiqing told a press briefing yesterday.

Given the general construction period of five years for a nuclear power station, China will witness the commercial operation of at least two units annually starting from 2011.

The company's efforts are a part of the country's plan to make better use of the clean and efficient nuclear power to increase the installed capacity to 40 million kilowatts by 2020.

In 2006, two of the CGNPG's working nuclear power stations, Daya Bay Nuclear Power Station and the Ling Ao Nuclear Power Station Phase One, with nearly 4,000 MWe (megawatt electric) of installed generating capacity, generated roughly 30 billion kilowatt-hours (kwh) electricity.

Specifically, Daya Bay Nuclear Power Station generated about 14.86 billion kwh electricity last year, of which 70 percent was supplied to Hong Kong market. This accounts for one-fourth of the territory's electricity supply.

The rest 30 percent and all the energy generated by Ling Ao Nuclear Power Station Phase One, which amounted to a little more than 15 billion kwh last year, was supplied by Guangdong power grid.

"The market is very potential. We have accumulated necessary capital, talent and experiences for the sector's fast development," Zhang said.

While reinforcing its advantages in Guangdong market, the company will also look for opportunities in other provinces, he added.

The phase two of Ling Ao Nuclear Power Station began construction at the end of 2005 and its two units, with 1,000 MWe of installed generating capacity each, will be put into service in 2010 and 2011, respectively.

The construction of another project in Yangjiang of Guangdong Province, which is expected to start this year, will be among the first group of nuclear power stations in China to adopt the third generation technology imported from United States or France.

The National Development and Reform Commission recently approved the first phase of Hongyanhe Nuclear Power Plant, a new project of CGNPG outside Guangdong Province, to build four generating units, each with an installed capacity of 1,000 MWe, from the previous two.

Hongyanhe project, co-developed by CGNPG, China Power Investment Corporation, and two local companies, is the first nuclear power station in Northeast China, which will be put into commercial use in 2012.



Top China News  
Today's Top News  
Most Commented/Read Stories in 48 Hours
主站蜘蛛池模板: 精品久久久久久中文字幕 | 最新日本中文字幕 | 91香蕉国产在线观看软件 | 亚洲第一网站 | 成年人在线视频免费观看 | 战狼4免费播放观看在线视频 | 国产区第一页 | wwwwww色| 国产一二三在线观看 | www.日韩精品| 手机天堂av | 久久久久色 | 视频大全在线观看网址 | 一区二区在线看 | 搜索黄色一级片 | 日韩精品视频网 | 在线观看国产黄 | 欧美日韩中文字幕一区二区 | 成人免费播放 | 国产免费一区二区 | 69久久久久 | 国产一区二区免费看 | 手机在线精品视频 | 粉嫩av性色av蜜臀av网站 | 99热这里只有精品5 www.四虎com | 成人看片黄a免费看视频 | 狠狠爱综合 | 天天色成人网 | 亚洲天堂一区在线观看 | 午夜a级片| 亚洲第三区 | 免费手机av | 色综合精品 | 国产少妇在线观看 | 亚洲免费专区 | 美女色网 | 日本一区二区三区在线观看视频 | 天天天天操 | 国产成人综合精品 | 亚洲男人天堂网 | 精品一区二区三区视频 |