NW China province to transmit power to Tibet

(Xinhua)
Updated: 2010-09-16 00:10
Large Medium Small

XINING - Experts approved a construction plan to transmit power from Northwest China's Qinghai Province to Tibet by connecting Qinghai and Tibet's power grids on Wednesday.

Related readings:
NW China province to transmit power to Tibet China's electricity consumption up 14.7% in August
NW China province to transmit power to Tibet Need for smart electricity grids
NW China province to transmit power to Tibet Failing power supply raises hot questions

China will spend 16 billion yuan ($2.37 billion) in connecting the grids during the next two years.

China's National Development and Reform Commission approved the construction of the grid on June 17. It will be completed and put into operation by the end of 2012.

Tibet's grid is not currently linked to any other grids. During the dry season, the region lacks power because about 80 percent of its power supply comes from hydro power stations, while in flood season, there is too much power.

After the grids are connected, the surplus power during the flood season will be transmitted to Qinghai or other parts of China through the Qinghai grid while power from elsewhere can be transmitted into Tibet during dry season, said Zhang Wenliang, head of China Electric Power Research Institute.

"It will be a world class power transmission project with high safety, efficiency and environmentally-friendly standards," said Wen Weibing, deputy head of the Qinghai-Tibet grid connection construction headquarters, State Grid Corporation of China.

The project will be constructed in three phases:

In the first phase, a 750 kV transmission line will be strung from Xining, capital of Qinghai, to Golmud City in the center of the Qinghai-Tibet Plateau;

Next, a 400 kV transmission line from Golmud to Lhasa, capital of Tibet Autonomous Region, will be hung;

Third, a 220 kV grid facilities within Tibet will be built.

The transmission line will run 1038 km from Golmud to Lhasa. About 900 km of the line will be built on lands that are at least 4,000 meters above sea level, making it the longest power transmission line ever constructed at such high altitudes.

Experts warn, however, that harsh conditions on the plateau might affect the workers' health along with their efficiency.

Currently, more than 4,500 workers are at the sites, involved in preparatory works. The number of workers is expected to reach 20,000 during its peak time, according to statistics from the construction headquarters.

The project has allocated 300 million yuan ($44.5 million)for medical care and environmental protection. First aid stations are being built every 25 to 30 km and clinics are to be set up every 100 km along the line. Workers will be trained in bases in Golmud and Lhasa to become accustomed to the environment before going to the work sites, said Fa Tao, head of the project's medical and life support department.

"Our goal is to ensure three zeroes - zero death, zero disability and zero permanent health damage for workers of the project," he said.

Another challenge for those involved in the project is to avoid affecting Qinghai-Tibet plateau's fragile ecology. "Whenever there is a conflict between construction and ecology, we will make way for environmental protection," said Yu Xinqiang, head of the construction headquarters.

The soil, along with the plants in it, will be taken away and preserved before a transmission tower is constructed. Then the soil and plants will be returned to its original site, according to the construction plan.

Workers are strictly prohibited from hunting or disturbing animals on the plateau. Also, transmission towers should be located away from animal habitats, according to the plan.

A section of 550 km of the transmission line will be built on frozen soil that could become unstable due to temperature changes. "Construction on frozen soil is difficult, but we have developed some technologies to ensure the project progresses as planned," said Ding Yansheng, head of the construction headquarters' technology department.

Experts note that with the experience of constructing the Qinghai-Tibet railway line, the world's highest and longest railway on a plateau, most of the project's challenges have previously learned solutions.

 

主站蜘蛛池模板: 国产精品毛片一区二区三区 | 在线观看精品国产 | 日韩中文字幕在线观看视频 | 欧美不卡在线 | 欧美一卡二卡在线 | 国产精品自产拍在线观看 | 中文字幕久久精品 | 亚州综合视频 | 91久久国产综合久久91精品网站 | 性色一区二区 | 国产又粗又长又黄视频 | 国产成人精品一区二区三区视频 | 成年人免费网站视频 | 久草福利资源在线 | 深夜做爰性大片108式 | 国产在线一二三 | 一区二区三区国产视频 | 欧美日韩国产在线 | 欧洲精品在线观看 | 午夜激情在线播放 | www日韩精品| 九九九九精品 | 久久精品波多野结衣 | 激情二区| 三级三级久久三级久久18 | 91久久久久久久久久 | 亚洲精品免费播放 | 国产精品视频免费观看 | 国产激情免费 | 国产福利91精品一区二区三区 | 自拍偷拍网 | 在线欧美成人 | 精品中文视频 | 国产精品第 | 午夜在线观看视频网站 | 四虎官网 | 亚洲啪啪 | 另类综合网 | 国产美女91呻吟求 | 日韩黄网 | 一区二区三区在线视频播放 |