World's tallest bridge progresses with steel truss milestone

By YANG JUN and LIU BOQIAN in Guiyang | chinadaily.com.cn | Updated: 2024-11-07 16:45
Share
Share - WeChat
The 215-ton truss lifted on Monday will be the primary support for the Huajiang Grand Canyon Bridge's concrete deck. [Photo by Liu Boqian/For chinadaily.com.cn]

Huajiang Grand Canyon Bridge in Guizhou province completed its first steel truss lift on Monday, marking a major step toward next year's scheduled opening.

Towering 625 meters above the Beipan River, the 2,890-meter-long bridge is part of a regional expressway project. Construction began in 2022. Upon completion in 2025, it will set a new record as the world's tallest bridge.

The 215-ton truss lifted on Monday will be the primary support for the concrete deck. It is one of 93 truss segments, weighing more than 21,000 tons, that will form the bridge's main structure.

Considering such a high weight, engineers deployed the world's largest cable crane system, incorporating transport, lifting and smart monitoring systems to navigate the challenging terrain of steep mountains and deep valleys.

More than 30 high-definition cameras and numerous sensors provide real-time data to ensure safe, precise positioning.

"The smart lifting system, developed in-house, uses the Beidou navigation and IoT technologies for precise positioning. The system improves both the accuracy and safety of the lift while reducing labor costs," explained Wang Songyu, the construction project manager.

Inside the bridge's smart control center, only a few operators manage the installation process, with the system reducing a task that once required 20 people to one that now requires only two operators.

Guizhou's rugged terrain has driven the need for extensive bridge infrastructure to support its traffic network. Once completed, the Huajiang Grand Canyon Bridge will reduce travel time between its two ends from an hour to just one minute, significantly improving local mobility and boosting tourism to nearby attractions such as the famous Huangguoshu Waterfall.

The project team said the construction is now 75 percent completed, with all the main cables in place. The remaining steel truss sections are expected to be installed around the Chinese Lunar New Year, and the bridge is on track to open in the latter half of 2025.

Top
BACK TO THE TOP
English
Copyright 1994 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
主站蜘蛛池模板: av中文字幕一区 | 欧美成人免费在线视频 | ass日本粉嫩pics珍品 | 丁香婷婷激情 | 中文在线永久免费观看 | 青春草在线播放 | 亚洲专区区免费 | 韩国久久| 日韩美女视频 | 亚洲激情一区二区 | 玖玖在线视频 | 国产精品一页 | 国产一区二区三区免费 | 在线欧美成人 | 亚洲一区二区综合 | 中文字幕在线网址 | 色婷婷国产精品久久包臀 | 国产精品一区久久久 | 欧美精品1区 | 久久精品国产成人av | 免费一级大片 | 91精品国产91久久久久久黑人 | 国产三级在线观看视频 | 天堂中文在线视频 | 久久国产免费观看 | 日韩三级视频在线播放 | 日韩精品福利在线 | 四虎国产成人永久精品免费 | 亚洲精品黄色 | 一级大黄色片 | 青青草原亚洲 | 毛片毛片毛片毛片 | 亚洲a网| 色婷婷欧美 | 亚洲欧美自偷自拍 | 欧美日韩成人精品 | 老色批av | 黄色av一区二区三区 | wwww黄色| 四虎成人免费 | 亚洲怡红院在线观看 |