Japan disaster plant's cold shutdown could face delay

Updated: 2011-08-18 08:16

(China Daily)

  Comments() Print Mail Large Medium  Small 分享按鈕 0

TOKYO - Tokyo Electric Power Co (TEPCO) said on Wednesday that it may fail in its bid to achieve "cold shutdown" at its tsunami-hit nuclear plant in Fukushima by January, as the world's worst nuclear crisis in 25 years rumbles on.

Efforts to decontaminate highly radioactive water at the facility have been delayed by repeated breakdowns of cesium absorption instruments, which have caused water leakage and malfunctioning of pumps, threatening to delay the process of stabilizing the stricken plant.

"It's possible that decontamination may not be completed as planned by the year-end, although we have not yet decided to change the target. That could affect the cold shutdown process," a company spokesman said.

His comments follow a similar statement on Tuesday, reported in the Nikkei business daily, from Junichi Matsumoto, a TEPCO spokesperson on nuclear issues.

Cold shutdown is usually defined as meaning the water in a reactor is below 100 C at normal atmospheric pressure, making its radioactive fuel safe from heating up again.

TEPCO also confirmed on Wednesday that it is testing a new radioactive water processing instrument as it struggles to cope with the damage wreaked by the 9.0-magnitude earthquake and tsunami that devastated the country's northeast coast in March.

With only an estimated 42,000 tons of highly contaminated water having been processed by Aug 9, roughly 120,000 tons are still left in the basement in turbine buildings and elsewhere.

TEPCO had set a goal of processing 200,000 tons of radioactive water by year-end since more water will be contaminated in the process of bringing the damaged reactors under control.

TEPCO officials and nuclear crisis minister Goshi Hosono were scheduled to hold a joint news conference on Wednesday to explain progress on work to bring the damaged reactors under control.

The test run of Toshiba Corp's cesium adsorption instrument, known as Sarry, is being carried out by running water with low-level radiation through equipment from French nuclear firm Areva SA and US nuclear waste management company Kurion Inc. It is scheduled to start operating fully as early as Thursday, Tepco officials said.

Sarry is relatively easy to maintain because it has fewer pumps, the breakdown of which have been a major reason for delays. Even if the system's overall operating rate holds steady at 90 percent, roughly 195,000 tons will be processed this year.

Reuters

Hot Topics

The European Central Bank (ECB) held a conference call late on Sunday ahead of the market opening, pledging the ECB will step in to buy eurozone bonds with efforts to forestall the euro zone's debt crisis from spreading.

主站蜘蛛池模板: 久久公开视频 | 性色av一区二区三区在线观看 | 亚洲欧美视频在线 | 婷婷综合在线观看 | 国产免费一级视频 | 伊人55 | 超碰com| 免费a在线观看播放 | 黄色片免费| 四虎影院在线免费观看 | 国产精品国产三级国产普通话对白 | 日本久久免费 | 国产精选一区二区 | 九九热在线观看视频 | 日本高清www | 精品国产一区在线 | 日韩一区二区久久 | 热久久免费视频 | 91av视频在线播放 | 亚洲欧美a | 国产精品美女久久久久av爽 | 色av中文字幕 | 国产精品一区在线免费观看 | 任你操在线视频 | 亚洲精品自拍视频 | 欧美 日韩 中文 | 成人毛片100免费观看 | 草视频在线 | 午夜av片| 日本黄色视 | 福利一区二区 | 2018天天操 | 午夜影院福利 | 网站在线观看你懂的 | 影音先锋每日资源 | 国产精品8| 五月激情婷婷丁香 | 欧美三级在线免费观看 | 日韩毛片在线免费观看 | 九九久久免费视频 | 777精品视频|